3 Week Basement Finish: How to Create a Construction Schedule for Your Project

Do you want to create an extra living space for your home? Do you want to make use of your basement area into some functional unit? If yes, you might be considering a basement renovation project. In order to start with a basement renovations Toronto project, you would need to take the help of a professional basement renovation contractor.

Homeowners on consulting a contractor can ask them to come up with a complete schedule for the project. Most contractors usually come up with a plan of partially finished basement in 3 weeks. Within the plan, a basement can be transformed into a family room, or study room for the kids, or a room with closet for clothes and dining space.

How to Break Up the Work?

In case, you are not interested to take the help of professionals and plan of carrying the project on your own, you need to be very careful. Renovating a basement is an arduous task and it should be carried by a professional.

basement renovations Toronto

 

Basement renovations Toronto experts usually divide their work in the following way. Check it below:

First Week: Rough-Ins

For the first week of the finished basement in 3 weeks plan, the basement contractors would divide their work in the following way.

On day 1 they will carry on with the framing the walls. It usually involves marking the concrete slabs in order to point out the door, windows openings, and wall locations.

On day 2 of the first week, framing around the ductwork is important. Usually, work around the HVAC system is done.

On day 3, the contractors on a finished basement in 3 weeks plan will start to work with the electrical roughly. They will ensure the basement is having the necessary electrical connections so that when a person uses the space they don’t face any problem.

On day 4 of the 3-week construction plan, work in on checking the insulation, installing sound insulation system in the basement and more.

basement renovations Toronto

Second Week: Sheetrock

During the second week, the basement contractors will carry out with their second phase of work. They will start to work with installing sheetrock in the basement area.

From day 5 to day 10, the basement contractors would work towards finishing the basement. Usually, they would hang down the sheetrock from the framework attached to the basement concrete walls. The framework needs to be plumbed with wedges before inspection of sheetrock starts. As a part of the finished basement in 3 weeks plan, doors delivered, shelving and trimming of sand sheetrock are done.

Third Week: Finishes

During the third week of basement finishes, on day 11, doors are installed. Shelving and trim are done. On the following day, painting preparation is done and primer coat is applied. After that, the ceiling, trim, and doors are painted. Following that the walls are painted.

As a part of the finished basement renovations Toronto in 3 weeks program, after painting the walls, the final work with the electrical, HVAC system is done. Hardware for the doors are installed and final inspection is done.

One should always list the main tasks and then come with a flow-diagram for the construction schedule. Scheduling date and time to the concerned person would help to finish the task within the assigned time-frame smoothly.